| January 2010 |
|
Moving in, planning the project |
| February 2010 |
|
Starting demolition |
| March 2010 |
|
Working in the garden, more demolition, starting the electrics and the insulation |
| April 2010 |
|
The builders get started, the roof goes on the yard and rooms start to appear |
| May 2010 |
|
Decorating, the log burner and solar PV installed, moving into the annex and starting work on the main house |
|
|
The solar thermal panels and the thermal store are installed, the new windows and doors arrive and the heating system is partly up and running |
| July 2010 |
|
Installing the new windows and doors, making the house habitable and getting the kitchen in, and being accepted for the Old Home/Superhome network with a carbon reduction of 91% |
| August 2010 |
|
Finally the old porch is demolished and the new garden room started, the front garden starts to come along and we make our first return for the Feed In Tariff |
| September 2010 |
|
The garden room is finished, work on the garden studio starts in earnest and the Recycled House opens for four days as part of Heritage Open Days |
| October 2010 |
|
Internal work on the garden studio, another open day for the 10:10 campaign, the final triple glazed window and the oak framed balcony |
| March 2011 |
|
A very belated progress update after a break over Christmas and the New Year |
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|