MANAGEMENT INTERVIEW - 4 JUNE 1999

 

The Management Interview re Joseph Bednarczyk was held on 4 June 1999 and was conducted by Martin Stubbs and Tim Barker in Tim Barker's office at 10.00am.  Satnam Thiara was in attendance as an observer. Management's questions are in bold and Joseph's responses, as recorded by management, and subsequent amendment following Joseph's document submitted 15 June 1999, are in blue. The items in black are Joseph's additions added via his document received by management 15 June 1999. The items in brown are JB's second lot of additions handed in 16 July 1999. There is also added, at the back of the document, a series of questions and comment from Joseph in the same document. These are also highlighted in brown..

 

 


You have already been spoken to on several occasions by your Management and in view of recent events the position has now become more formal.

 

The letter shows the areas which we intend to cover in the Management interview which you should answer as fully as possible following which your Management will consider what action to take which could include formal disciplinary action.

 

A discussion took place regarding the procedure and Joseph requested that he be allowed to consider all his answers as he wished to give full answers.

 

CUK3

 

1.         Why did you not inform David or Martin regarding this issue?

 

I told you both about it as soon as I realised that I wasn't going to be able to do this. Told Dave around the first week in April. Told you a few days after.  Only realised in Early April that it was too complicated.

 

 

DL states that it was third week in April. Why did it take so long?

 

It may have been a little later but I told DL as soon as I realised.  DL may have seen you a few days later.  Things went backwards and forwards and DL asked me to tell you personally.

 

This question asked why I did not inform DL or MS regarding this problem. I did inform both of them as soon as I realised that this was going to be the case.

Background is needed to this subject to get a clearer picture of what is being discussed. This spreadsheet, as most of the other automated procedures within Income Control, were devised by myself as part of the overall Control procedures. I set up all of the processes within Income Control to alleviate the Control staff of many of the more repetitive functions.

There has never been any obligation on my part to produce this level of sophistication but this has been done to show my commitment to the work involved within Income Control.

The CUK3 spreadsheet was a project that I set up by myself, done mostly in my spare time at home. There was no assistance from any other members of staff or management. It was a project that I set up to show management that the information they were receiving could be presented more efficiently. 

The original work was done at a time where the workload within Income Control was not as heavy as it is now. Since then, many new functions have been taken on board and to spend the time required dealing with this type of project has become impossible.

Each year, I have historically taken this project home with me and updated the spreadsheet in my own time. This is because I feel proud of the work that I do within Income Control and feel as though I did not mind spending time at home keeping up to date with the processes and also updating the finished products.

This has not been possible over the past year and I have found progressively that any updates needed on this particular spreadsheet have become harder and harder to update. This has been mentioned to management over the past year or two but no assistance or efforts to help or to backup this procedure have ever been offered.

 

When I finally came to this conclusion regarding the spreadsheet, the reaction from MS was aggressive stating that he would cancel the NVQ I was involved with. I was shocked by his response stating that my IT skills were being put to good use on many other projects apart from this one. Just another example of management harassing.

This should have been no shock to management who had been told on many occasions as to the increasing complexity of this particular project. I feel that they have been very fortunate to have this extra work given to them free of charge over the past few years. Instead, the reaction is an insult to the amount of work that I have put into this spreadsheet over that time

 

Why did you not tell us earlier?

 

It was becoming increasingly complex and taking time to put right.  I do it at end of March early April every year but I couldn't understand it, I'd forgotten so much.

 

I told management as soon as I realised this was going to be the case.

 

Did you not look at this in January 1999

 

I do look at this during the year approx. 6 or 7 times to correct information but not to go into visual basic which is where the difficulties are.

 

This is true but each year the whole updating procedure becomes that much more difficult. The work I do during the year is just to make sure that the current week produces the correct information.

 

2.         Can you explain how Francis Smith knew about this problem before your management?

 

No. Can't remember telling her but may have mentioned it in passing

            Everyone knew it was complex and I told her it was difficult.

 

This question has no relevance to the original problem but I did answer it as stated. I deal with Francis on a regular basis regarding Working Practices. This may have been mentioned as it does impact on a change to the current workings of the section.

I cannot remember in what context it was mentioned or why it was mentioned before informing management of the problem. It is not really an issue. The fact was that this spreadsheet had now become too difficult to maintain. This is supported by the fact that no-one else in the whole Income Unit is able to deal with this spreadsheet. Surely management should have realised this a long time ago.

These questions are just trying to hide the issue of why was there no attempt by management to train either themselves or even other members of staff to deal with this type of information presentation when they had been told of the continuing complexity on many occasions.

Did you tell her you were not doing it?

 

            No, or maybe yes but after I had told Dave.  I can tell who I want.  We were probably having a discussion about working practices and the CUK3 was mentioned.  I would have told her if she had asked me but I am not sure when.

 

I did not say “I can tell who I want”. What I was saying here was that if I am asked a question regarding issues which affect Working Practices, then I may have mentioned it.

 

Notes from management concur that this was actually said during the interview

 

3.         Can you explain how Richard Carter knew about this before management?

 

            The same. Within a day or so he came down with a query, I can't quite remember, it may have come out in conversation.

 

Richard Carter is a user of this spreadsheet apart from many other spreadsheets which I have designed. The topic of the CUK3 probably came up in the conversations we had around that time.

 

Do you think it appropriate that others knew before Management?

 

            There was no reason to tell others before Management, Management should know first.

 

Again, the question here is not whether others should know about a spreadsheet which I have designed before management but an issue of hiding behind other questions.

These first 3 questions relate to an issue which should have been resolved a long time ago. Management have known for many years regarding this issue. The fault is with their lack of co-operation with the work I have been doing, not the other way round. Their lack of support for this project in terms of any training for any of the Control staff or other members of Systems to be able to backup any problems with this spreadsheet has brought this situation about.

After all this, I am now being harassed by them over side issues to try to hide the main issue involved here – one of lack of management planning and support.

 

4.         Manual figures for CUK3. Did you say to Dave that control would not be able to fulfill MS' request to have the CUK3 figure because Lynn Armstrong was too busy doing refunds?

 

            This was about control priorities.  I asked, "which would you like to be done".

 

            Martin repeated the question.

 

            DL asked for it I said it would take a while to do manually but if needed obviously I would do it.

 

            Martin repeated the question.

 

            I don't know, I didn't say I liked standing on one leg.

 

            Martin repeated the question.

 

            No.  Lynne had nothing to do with it, I was going to explain how to do it to the staff but Lynne had not been shown how to do it at that point.

 

Ash sent the figures to MS that same day

 

This was not the answer I gave at the interview. MS asked me if I had said this to Dave when Ashraf had sent the manual CUK3 to him at home via e-mail. I replied that Lynn had nothing to do with the CUK3 for that week.

A background is needed to this as well. The CUK3 was originally a printed report which Control would receive and pass over to MS. He would extract the details from this report and generate his own statistics. My efforts to produce this spreadsheet showed that this procedure could be greatly streamlined and made more user friendly.

When I told MS that I would be unable to continue with the spreadsheet, his reaction was aggressive and his tone sounded on the tone of “I’ll get you for this”. I was very shocked at this. In a meeting with DL and MS later, MS told me that he wanted Control to provide the same statistics but this time on a manual basis.

This has added many hours of entering data into a template to get to the required totals. You have to remember that this process was formerly performed by MS and Control were only the delivery agent.

I have started to train staff in the methods needed to produce this report. I have designed the template for them to use and they were to take it in turns to produce the statistics.

The first week was spent designing the template with Ashraf Hussain who helped to enter the data. The process took around 6 hours to complete.

As stated, I helped Ashraf to complete the manual CUK3 on the first week. This was sent to MS at home.

The week after, I asked Lynn to complete the CUK3. On Wednesday afternoon, I asked her if she was ready to start the work. She replied that there were plenty of refunds to do that week and she was busy completing them. The deadline was Thursday. I mentioned to DL that there was a resource problem if Lynn was to spend the number of hours needed to complete the CUK3. He suggested that Juzer should help with the refunds and Lynn would tackle the CUK3. I agreed to this.

There was no confusion here but an allocation of resources

 

Management notes confirm that this was in fact what was said during the interview

Risk Assessment of Automatic Tasks

Your E-mail of 4 May 1999 refers. 

 

5.         A list of processes "subject to melt down or which could not be supported in his absence" was requested in order that Management could make an informed decision whether to accept the risks and look up back up procedures if this did occur.  Why did you not send this E-mail to Management in the first instance?

 

It was an error I am used to sending a template to all.  I don't send everything to staff that goes to Management.  I realised afterwards.

 

The answer in the interview was given without reading the e-mail again. On reflection, the action I took was correct and in compliance with management directives.

 

On 24/04/99, in a meeting with MS and DL, I was told by DL not to use procedures which the System Technicians could not update.  After the meeting, I sent an e-mail to DL to clarify this issue. The e-mail read as follows:

“Would you clarify the directive you made this morning, by-email or letter that I should not do any more work on spreadsheets etc that cannot be updated by the System Technicians.

 

This has very serious repercussions for the work done on Control and I need confirmation of this before putting this into practice.”

 

Following on from this, MS sent a management letter dated 30/04/99.

This e-mail regarding the changes was sent to DL on 04/05/99. I am used to sending any issues affecting Control procedures to the team as well so that they can be kept informed. I use a template to do this. The template has the Control team as a cc: recipient.

Thinking it through, I cannot see any problem in sending this to my team as a cc: through e-mail. They should be kept informed of any changes which need to be made on Control. The changes needed are to set up manual procedures in case there is a problem with the automated process. The Control team needed to know about this for when I began to set up the manual procedures as a backup.

D id you do anything about it?

 

The E-mail came back from DL shortly afterwards to say he wanted to discuss it.  I think he also came round and said that we needed to answer each point and should continue using the current procedure which I have done since then.  There is no problem there.

 

The following e-mail was returned by DL on 07/05/99 after my e-mail of 04/05/99 explaining the changes that were needed.

“Just so that you are aware I felt the need to talk to the technicians yesterday to reiterate that they were still to undertake the tasks you listed in your email of the 04/05/99, as I confirmed to you verbally and in a return email on the same date. This will be the case  until such time that the issues contained in your email can be addressed properly.

Thanks Dave”

 

Considering the emphasis in MS letter regarding the complexity issues, nothing has been done by management over the past month to address this issue. How is this possible when it has been highlighted in a management letter as a serious issue.

 

7.         Why did you write an instruction "the following areas are to be reverted to manual procedures" when my letter and Dave's verbal instruction were for you to carry on and doing a risk assessment?

 

It should say 'Begin'.  A slip of words - didn't really mean it

 

If this is read in context in my e-mail, you will notice that the paragraph follows on from the previous two where I said that “these are the changes which need to take place for this to be put into effect”.  I then went on to explain the changes that would be needed. This is how the paragraphs read:

In the letter from MS dated 30th April 1999, I was told to give you advance warning of any procedures where the complexity of the current process is too much for a technician. The following areas fall under such a heading and need to be addressed.

Also, to comply with the new management thought on the way Control procedures should be documented, these are the changes which need to take place for this to be put into effect.

The following areas are to be reverted to manual procedures. Then, in line with System Technician skills, new methods will be applied which means that the overall process will not be dependent on just one individual to maintain.”

 

 

MS is reading this completely out of context. The paragraphs are simple enough but it seems that MS is trying to look at any phrases that can be interpreted to support his allegations, even though they are not, in any way, designed to be non co-operative with management. Rather the opposite if you were to read the whole e-mail. I spent time highlighting 26 areas as soon as I had received his management letter. I cannot see why this is being used as an argument for non-co-operation. Obviously, MS is getting desperate to find legitimate items that will support his very biased viewpoint.

Again, this supports my view of management harassment which I have been experiencing from both MS and DL.

Also, MS letter stated “if advance warning is not possible, then alternative procedures should be available to handle tasks that are complex and may be subject to ‘breakdown’. Presently, because of the way procedures have been designed, there are no alternatives to the automated procedures.  Working practices should be changed to cope with this so that in case of problems, the manual way of accomplishing these tasks would need to be documented.

I know that in the interview I said that the word “begin” was a slip of words but this was only because I did not have the narrative in front of me. The wording is correct, as the manual procedures would need to be started immediately to cater for manual procedures in case the automated procedures were to fail.

The final part concerning DL instructions. These instructions came only after the e-mail had been sent and this instruction has been complied with every detail.

Why are you making these allegations and wasting both my time and management time? It seems MS is taking everything out of context just to try to prove his allegation that I am being non co-operative with management. The opposite is much more the case.

The harassment I am receiving from both MS and DL is making performing the Control function almost impossible.

 

8.         Did you also tell Francis Smith verbally about this issue after receiving DL's response and his verbal instruction?

 

Don't remember, I've slept since then. I may have discussed things with her during our working practice sessions.

 

My answer was that this may have been mentioned to her during our Working Practice sessions. If these procedures did have to be reverted to manual methods, it would mean a change to the Working Practices.

 

9.         Hypothetically, if you were in this situation would you have said this to her?

 

Why should I say this if this is not what the procedures are. I may have mentioned to her that things might be changing though.  It's not my decision at the end of the day, I can't see a reason why said that, maybe said maybe a strong chance.

 

I remember that I repeated the answer to point 8.

 

Whilst the content of this answer remained the same, the manner in which it is recorded above is correct

 

10.       When Peter Norris requested his usual report the day after your E-mail and verbal instruction why did you give him the paper copy.

 

Delays were caused that Monday that meant that all output was late. Paula Briggs passed the copy to Peter.

 

Answer is correct. Paula passed the report to Pete Norris inadvertently. The instruction is to file the report and send the downloaded copy to Peter.

 

 

11.       Was this because you were now following this new procedure?

 

No, it was because of the delay

 

Answer correct.

 

12.       Did you question why Peter needed this report electronically.

 

No, I discussed the best way that he should get it, Excel or Text file.  This was part of my master plan I started a few years ago.

 

Answer correct.

 

Did you question why he needed it in electronic format?

 

I don't think so.  Him and DL came round.  It was sent that afternoon, there was no problem with that.  These were processes which systems technicians couldn't do.

 

Peter and DL asked me why the CU32 had been passed around in hard copy. I explained that Paula had passed it inadvertently and the downloaded copy was a little late in arriving this week.

 

I determine high risk as where there is no alternative, is there an alternative?

 

There is a manual alternative to all of these just the same as the CUK3 except it just takes a lot longer.

 

The answer to this was not full enough.

There is an alternative to all of the automated procedures that have been set up but it means that I will have to train staff in these areas and also amend the working practices.

The current working practice is to press a macro button and the procedure will be performed. These automated sessions are all documented but the manual sessions are not.

If there was a problem with any of the automated procedures and I was not available, it could lead to a situation where the manual process may be performed incorrectly or not at all.

13.       Are these high risk areas?

 

That’s up to Management to ascertain. They can all be covered with manual procedures. These were processes which systems technicians couldn't do.

 

Answer correct.

 

14.       What was the purpose of the final paragraph and was it appropriate given it went to all staff?

 

Yes it was appropriate.  It was a genuine remark and not a sarcastic comment, It was not intended for the rest of Control to see but I hoped nobody else saw it as a sarcastic comment and got the wrong message

 

Did you think DL saw it as sarcastic?

 

That's up to him.

 

This remark was appropriate. I have been working on Control procedures for many years and maybe there are areas which could still be improved even though they have been working well for many years. Not a sarcastic comment.

 

Sanderson Software

 

15.       I asked for you view on the Sanderson inspection procedure on 2.2.99. You did not respond so I followed this up with some alterations on 8.2.99. These procedures involved control running various jobs.

 

Why did you not respond to this?

 

I have given this answer on many occasions.

 

Joseph requested time to consider answer.

 

16.       Once this became an issue, you met with DL in MS' office for approx. 3 hours, and said you thought he was joking.  What did you find was amusing about this.

 

Joseph requested time to consider answer.

 

Hardware Inventory System

 

17.       Quote from Martin letter.  David had made repeated requests to you to spend just 5 minutes to look at the software.  These requests were ignored, why do you think that is appropriate?

 

I was too busy.  It was not specialised enough for our needs. I had downloaded it from the Internet at home and looked at it already. We needed something tailored.  I took it on board to look at it but it was not a priority.  I was asked for it by a Monday date, I have other specific priorities so I didn't do it.  I subsequently spent 40 minutes with Robeena Khan and then repeated my same comments that I had mentioned a week earlier.  Why such a big issue about a little thing?

 

Why did you ignore the request?

 

I have mentioned already it was not a priority, I had given my concerns as I had looked at this at home, I did make efforts in the first instance, my time was wasted as a Team Leader that can be used more beneficially.

 

But DL wanted this - the question was repeated.

 

I still can't understand this. 

 

This answer has not been documented properly.

I was asked by DL to take a look at this software previously. I had discussed this with him at that time. I spend a fair amount of time on the Internet and had downloaded the same software at home. I knew what this was like. I did not consider that this was relevant to the specialised needs of the Income Control team and gave my reasons.

As I had already given my “valued opinion” (as had been requested by DL) on this subject, I did not consider this a priority. DL had asked me to take a look at the software even though I had explained why this was not appropriate to the needs of the team.

I left important work on Control to spend 40 minutes with RK looking through the software. I showed her the current Control inventory which is far more relevant to our needs. My suggestion has always been to bring up the Control staff to a level where a database is designed by them on Access which can then be updated as the needs of Control change.

This 40 minutes resulted in passing the same appraisal of the software to DL as I had given originally. The time I have on Control is very limited to do what I need to do already and I could see no reason why I should spend time on a very low priority issue which I had already answered. I did intend to spend time with RK to comply with DL directive but it has been difficult to find the time to do this. Control functions take all of my time especially with the needs of training new staff and keeping the current staff updated with the latest developments.

This is just an example of what I consider to be management bullying. This was not an operational issue but just an example of management using their authority just for the sake of it to show that they could make you do what they want regardless of its value.

The answer has been document according to the notes take by management on the day

 

18.       You stated when you met MS/DL on 22.4.99 that you had set up a meeting with Robeena Khan, which had not been set up, can you explain?

 

I never said this in the meeting and I had not set anything up.  I said I'd do it today.  I intended sitting with her that afternoon and did.

 

This answer is not as I remember answering the question.

I remember in our meeting with DL and MS that I was asked about this Inventory question. I had explained what I had already told DL previously but this was not acceptable to MS and DL who were very heavy handed about this wanting me to have a look at the database again.

I felt as though I was being bullied into this. It was no longer a question of taking a look at the database as this would be a waste of time but it was a matter of “you will do whatever we say no matter how stupid it is”. I remember feeling that.

I did tell them both that I had intended to take a look at the database that afternoon. I had intended to take a look at the database on each day since I had been requested to do this by DL. With the amount of work on Control and the low priority of the database in my overall task list, I just had not found the time to do it.

I did sit in with RK that afternoon, pushing other far more important considerations to one side just to comply with this management request. After 40 minutes in which I had explained the problems in using the Primasoft database for Control Inventory purposes and then showing our own database, I repeated what I had told DL after the original request. I had wasted 40 minutes of my time but at least management were satisfied with themselves.

Notes from management concur that this was actually said during the interview

 

19.       Meeting on 15.4.99 E-mail requested you attendance and was ignored. When Dave approached you, you claimed not to have received the e-mail, then that you had not read it, then that you had forgotten? Why was this

 

Just back from holiday I had 30/40 e-mails. Had read it and forgotten it - it slipped my mind.  Normally I remember.  This is so petty, so fickle.

 

The meeting itself was taking place just a few yards from my desk. To remind me on the day of the meeting would have been no inconvenience at all. DL, RK and myself had attended the IT Meeting prior to this meeting. To call this a gross non co-operation with management requirements shows how desperate MS is to find areas which he can use to substantiate his claim. I consider this to be management harassment and intend to take action of my own

 

 

Audit Report on Storing Cheques

 

20.       Repeated requests were made for your comments on the report, you stated you would provide by Monday but by a meeting on Thursday it had still not been done.  A systems technician took less than an hour to do a response, can you explain?

 

Apologised already for this. Did not think it was a high priority. No other reason behind this.  I thought there was no rush, so I put in in a pile.  Normally audit report's take 2 minutes as the control procedures are good.

The response shown in the transcript is very abrupt. I did not intend any of my answers to be heard in this way. The reply should read as follows:

I have already explained this in my reply to the original letter from MS. In that reply, I did apologise for not seeing MS on the day he suggested. I cannot remember the exact details of what happened at that point in time but I remember MS dropping the report on my desk and said “no rush” as he zoomed off. This is his normal style of interaction and you have to be quick to catch what he actually wants to say.

When I read the report, the changes needed were very slight and not urgent. They would have taken 5 minutes to implement. I amended my Dataease system to partially take care of the Audit report and was going to finish off the changes after I had seen MS. Due to pressure of work and other commitments, the report was on my desk under other papers for a few days.

The Systems Technician who dealt with this while I was absent took a folder and drew 5 lines down the middle. Not a big problem.

Although I cannot remember the exact details of this, I do always try to meet any management requirements. There are times when I am ready to go to see MS or DL only to find that they are currently occupied with other members of staff. When this happens, it is very easy to lose track of these things as Control can be a very busy place to work.

Again, to call this an instance of non co-operation with management requirements is “scraping the barrel” and falls more in line with management harassment.

 

Printer Software

 

21.       This was not examined until 3 months after the original request, why did it take so long to get back to MS (after chased by DL). Can you explain?

 

Did not think it was urgent. No deadline given when originally requested.  I thought you said have a go if I had time.  I was interested in it but didn't get time. 

 

Again, the reply here is not the way the reply was intended.

A slightly fuller explanation should be heard.

This software was from Hewlett Packard and deals with holding forms on the printer memory rather than passing the information to the printer each time the form is required.

The software was passed to me a few months ago by MS when it had arrived. He suggested that I would be interested in taking a look at it. Again, it was emphasised by MS only if I had the time. I have an interest in this type of software and would have liked to have been able to work on it.

The software is related to the Sanderson system. Originally, I was under the impression that Control would be in charge of the production of all the NDR documents under the new system. If this was to be the case, then it would be an advantage for Control to learn how to use this software. As the Sanderson system problems increased, I was told by DL that Control would not be needed to produce any of the documentation. This would be done by the NDR section themselves.

I was asked by MS at various points along the way as to how I was getting on with the software but the answer I had to give each time is that I have not had the time to take a good look at it. I did load it onto my machine but, with the constant pressure on Control, it became less and less a priority as we would no longer be producing the output.

When DL asked about this software, he told me to return it to MS if I did not have the time to take a look. This I did within a day or two, reluctantly, as I did still want to take a look.

The more appropriate place for this software is, of course, with the team generating the output. MS could have asked for the software at any stage of the proceedings as Control would not be involved with the production of this output but did not do so. Only now does this surface as being a non co-operation with management issue.

There was no specific deadline given by MS for this from the day the software was passed to me. There was no priority assigned to this software. MS knew that Control would not be dealing with the output and should have given me more feedback as to what was expected. As far as I was aware, there was no expectation after learning that we would not be running the Sanderson output.

Leave booking and overtime notification arrangements

 

22.       Why do you think that you do not need to book Holidays with DL first?

 

I do know that I must.

 

Answer correct.

 

23.       Following an incident where you didn't book leave with Dave Lickley you were told verbally and a memo was sent dated 1 July 1998. 

 

He asked me to complete an Excel sheet for this purpose and I thought he looked at it regularly. I put the holiday on this and asked DL at the same time. I have no idea why he sent the memo. There may have been problems between moving from GM to DL. GM let me ask him, then he'd put it in his diary. DL needs a memo. In all my twenty years I have always done this.

 

This “so-called” non co-operation with management is the result of an over reaction by DL, as, unfortunately, is the case for many situations.

Booking holidays has never been a problem on Control. The procedures are very informal and friendly and have worked very well for many years. This was also the case where I booked holidays with the former manager, Girish Mistry.

This informal arrangement entails the good nature and common sense of the members of staff employed on Control. All staff try to make sure that the section is going to be reasonably staffed before booking leave. If the section staffing is low, then I will usually refer them to the line manager to obtain his acceptance.

Booking my own leave was much the same. I would ask Girish if I could be off on certain dates and he would usually agree and mark this off in his diary. This was never a problem area before as I always make sure that my section was fully covered before taking time off.

I am sure that I also verbally asked DL for the days off at the end of August and beginning of September 98. I made this request in June 98 giving plenty of notice and making sure that the section would also be covered during this time.

Also around this time, because of the shortage of staff, prior to recruitment, I was asked to give DL a list of the section holidays for the next 6 months. I did this on an Excel workbook showing all of the holidays booked by all staff in this period. My own holidays were also shown on that spreadsheet. DL had constant access to this spreadsheet which I took as being the reference for the next 6 months.

After this, I was questioned about my holidays by DL. You have to remember that this was in June and the holidays were not for 2 months. I explained the situation, which at the time did not seem to be a problem. Then the letter arrived which led to a very heavy-handed approach to booking holidays.

DL stated in his management letter that as his two development officers were off on one of the two days I had requested, he would have to cover both sections. This was not the case as DL did not get involved at all with Control functions and has little idea on how to deal with the majority of the functions. The Control section has been well trained to look after the affairs of the sections themselves while I am not at work.

To have to come into work on that day, 2nd September, would have meant to break up my holiday in the middle to attend work when the Control section would have been well covered anyway. His approach to booking leave has left a stain of unaccustomed formality which has detracted to the smooth working of the sections.

Regardless of my feelings about his approach to booking leave, I have nevertheless adopted this method with DL as it was a request from management.

This was just an example of DL stamping undue and excessive authority on a situation which had run well for many years. A heavy handed approach like this was totally unnecessary and created a bad feeling for all concerned.

 

24.       A further incident happened on 17 February 1999 when you did not formally request leave, can you explain?

 

Chris was asked and OK'ed it

I was asked to tell an SO if DL was not there.

 

The leave in question here was a ˝ day flexi which I had been thinking about since earlier that week. I had not decided upon this until that morning. The section was fully covered. I always ask the staff if there are any problems which needed to be resolved.

After making sure that everything was working well, I sat in with CN and mentioned that I would not be at work that afternoon. MS substantiated this at a meeting with DL saying that he heard me talking about this with CN on that morning. As far as I remember, the Development section was adequately staffed as well

I did not send an e-mail on this occasion as DL would not receive it until he returned from leave.

 

Why did you not ask MS?

 

There was nobody there to ask, you were not around the section was covered there was no real need to tell someone.

 

MS was not available at the time and I did not feel as though this was needed. I had been asked by DL to ask an SO if he was not around. I did this by asking CN.

 

25.       Why does this conflict with my note of 25.2.99 meeting where you said nobody was about?

 

You are getting mixed up with the first refund run. That is what I meant when I said nobody was about

 

My reply to this was that MS was getting his wires crossed with an e-mail I had sent. This asked for a response to a query concerning the first live refund run on the Sanderson system. When this run had been scheduled, no senior officer was present all afternoon within the System section. This led to difficulties in completing the refund run on the scheduled day.

 

26.       An express instruction was sent out on an E-mail 8 June 1998 requiring overtime working to be requested/notified to Dave Lickley, you ignored this instruction by allowing and doing overtime the next day without reference to Dave, can you explain?

 

I do not recall this incident.  Sorry, isn't this resolved?

 

In the interview, I could not recall this but have since thought back and remembered that this was due to a misunderstanding. It would be hard to tell DL what we would be doing on a daily basis before the event as this depended on the workload at that point in the day.

The details of the overtime would be logged on the overtime sheet on the following day.

           

27.       But you were spoken to about it by DL the following day?

 

I still do not remember it

 

After speaking to DL on the following day, it was realised by both DL and myself that this was due to a misunderstanding. Our understanding was that we would mark up the overtime activities on the following day. After speaking to DL, this became the accepted routine. No problems after the initial misunderstanding.

This is not an example of non co-operation with management requirements. I feel that DL greatly over reacted to this, which was a misunderstanding felt by all of the members of Control at that time and not just me. The problems here were due to DL not thinking the procedures through properly in the first place and then taking a heavy handed approach rather than admitting his lack of clarity.

28.       Other Issues regarding colleagues outside the Section. Can you explain to us why there are all these incidents to deal with

 

            There are a lot!

 

I don’t remember saying “there are a lot!”.

 

Notes from management concur that this was actually said during the interview

 

a)         Lorraine Hawkes - an incident where Lorraine felt she had to "beg" for the store room key as staff needed access for the weekend, can you explain?

 

I do not recall this.

 

You were described as obstructive

 

Oh the incident over the storeroom key. It's our storeroom.  I asked why she wanted it and to give us a note for the inventory.  I'd say that to anyone.  This was resolved quickly and is no longer an issue.

 

This has to be the most ridiculous example of what has been termed non co-operation with management requirements.

Lorraine arrived on Control and demanded the storeroom key. I just asked what she wanted this for as the usual procedure was for my Control staff to put items in and take items out of the storeroom and keep a note of the inventory numbers for our records.

She said, “Just give me the key”. I asked her again what she wanted it for. She then said Dave Lickley had told her she could have it. I asked DL about this and explained that Control needed to maintain the inventory. HB had been know just to take items out and put items in without leaving a record of what had been displaced.

DL said he would make sure that this was done.

DL did not seem to understand how our procedures worked.

These situations arose from DL’s lack of understanding of our procedures.

If I did not question anyone’s intentions when they ask for the storeroom key, I would not be performing my duty as custodian of the equipment within the Income Unit. The same can be said of any Control staff. I am sure they would have responded in the same way.

It does seem as if I even sneeze the wrong way, then MS will take this as grounds for a management interview.

The effect of blowing up all these extremely minor instances to disciplinary proportions is extremely demoralising and demotivating. That has been the method that both MS and DL appear to have adopted for a very long period. It is credit to the Control staff and myself that procedures are still working well and efficiently even after this type of attitude.

b)         David Bacon - quote from the statement - please explain?

 

A one off incident, Francis Bacon and I are good friend again.

 

Francis Bacon, I thought it was David.

 

Oh yes

This was a one-off incident where things needed to be clarified between Machine Room and Control. This section had been accused off making errors which were actually the fault of the Machine Room.

These have not happened since and the problems have been resolved amicably. Working relations are fine.

Again, this has been blown up out of all proportion by management.

If there is a situation which is affecting the smooth working of the Control section, then I feel that I must act in the best interests of the section. It was brought to my attention by various members of staff at the time that claims were being made of Control mistakes which turned out to be errors on the part of the Machine Room staff.

I remember taking a phone call from the Machine Room, from David, who made a comment about all of our errors. I replied that this was not the case and that he should admit to any mistakes they make as I am sure Control staff would. This caused a quick exchange which was sorted out very quickly. With the air cleared, the relations between Control and the Machine Room were back to normal.

I feel that I have to support my staff when these issues are brought up. To deal with these issues is part of my function as a Control team leader. If only I could get the same type of support from my management, then things would go a lot more smoothly.

The only response is that if anyone makes a complaint, there is no support for my side of the argument but I am always seen as the guilty party by MS. I cannot remember a time when I was supported by my management.

 

c)         Julie Wear - quote from the letter - please explain?

 

She was complaining about my teams ability. I had to question this. Everything resolved now though. 

 

There are not many only 4, these are not big incidents.  I haven't smacked anyone in the face.  They were sorted in 5 minutes.

 

Martin pointed out it took him a lot longer afterwards.

 

This situation resulted from a phone call passed onto me by Miscellaneous regarding a number of invoices which had apparently been sent out instead of being returned to the user.

She had previously spoken to Pretash Govan who informed her that we had a new member of staff who may have made the mistake. I spoke to Ashraf, the new member of staff to see if he was clear about the procedures. He was clear about the procedures and said that he was sure that he would have returned the output to the users as stated in our working practices.

There had been occasions previously where the output had been passed to Miscellaneous first via a pullout request and then posting errors had been made by other staff in posting out the invoices. Other investigations have shown other explanations. I am always slightly reluctant to accept blame for the members of the section before investigating the incident.

The point I made to Julie was that I talked to my staff and they were sure they had sent the output in the appropriate way. Her reply was that she was sure the fault was with this section. I did apologise if this had happened but could not lay the blame on any staff as they deal with this type of output every day and are familiar with the procedures.

I did suggest in an e-mail that where there were very sensitive issues, then the output could be collected from the Income Control section direct and I think this offer has been taken up on various occasions.

She did agree that, overall, the service which was being provided was excellent.

I put an additional working practice into place where her output would be sent in a sealed envelope in future which would highlight that additional care should be taken and that no third party could open the contents without breaking the envelope.

These procedures have been adopted and work very well.

My efforts here were to make procedures better and more efficient. This has now been used by MS as a non co-operation with management issue.

It makes me wonder if there is any point is making these efforts to make procedures on Control more efficient and effective when all these efforts are just going to be used in a future management interview.

d)           Benefit invoices with N Woodhouse. Refer to the Girish Mistry incident re. general attitude and behaviour.

 

Don’t remember this one, although it will be resolved now

 

I would like to see a copy of this letter. From what I remember in the interview, it dated back to  Aug 97 which is two years ago. I cannot remember seeing this before but did remember the so-called incident which may have sparked it off. If this is to be used as an indicator of my general attitude and behaviour, I would like to be able to respond to the letter itself.

When Control took over Miscellaneous output, the procedures were found to be out of date and very inefficient. One of the many changes that were made to these procedures was to use Internal Mail to deliver the HB invoices. Nick said he wanted them bringing down to HB. We replied that they would be either left in Control for them to pick up or would be delivered by Internal Mail.

The internal mail was adopted and has worked very well since it was put into place.

There was no real problem with this interaction. The problem was when someone complained to management and they took the line that Control are always wrong. This has been the case throughout my stay under MS. Everyone else is right and what we are doing is wrong simply because someone complains. There has been little support from MS although the procedures which have been developed have shown many benefits.

 

Copy of memo sent to Joseph with this statement 30 June 1999

 

29.       Looking at the statement from G Mistry, it says you should work on relationships. This was 2 years ago and still these occur. Why?

 

No answer I can recall

 

I cannot say I have seen the document which I was shown. I do remember talking to Girish about this issue and have made great efforts with all interactions since then.

 

 

 


The following was added from JB's second amendment to the 1st statement received on 16 July 1999

 

The letter from GM dated 13 th August 1997

 

I cannot remember ever seeing a copy of this letter but I think I can answer some of the points raised and hopefully, show a more balanced view of the events which led up to this letter.

1 .      The first line "once again the Misc.  Revenues staff have voiced their concerns to about your approachability".  Although this sentence does not make sense, I will try to reply as to what 1 believe the issues may have been.

2.       This was certainly not all Misc. Revenues staff who voiced their concerns. I suspect that this point was raised by one individual who had the ear of his manager, who then proceeded to pass this onto MS.

3.       As with all other complaints, whether valid or not, MS always took the view that Control were in the wrong and 1 have no doubt that this was yet another example.  Instead of investigating what had happened and the reason behind this or giving support to his Control team, MS does always like to hide behind these types of letters.

4.       This was around the time that Control had taken over the responsibility of the miscellaneous output.  This was a decision taken by MS that Control should deal with the Miscellaneous output on a daily basis.

5.       The method used by Miscellaneous was very dated.  To have taken the methodology on board within Control would have put our own methods back by around 1 0 years.

6.              I set about designing a computerised system that would streamline the process.  This was employed and has been successfully in halving the amount of time taken to deal with the output as well as creating a database for any statistics needed.  There is literally no paper used in our side of the operation.

7.              Miscellaneous managers appeared to be against Control having any involvement in their system and this news was greeted by them with a certain resentment.

8.         The original request from Miscellaneous was for Control to duplicate the original practices that had been used by them for many years.  The changes resulted in considerable savings overall with increased efficiency but it was a difficult task to persuade the Miscellaneous managers of their worth as they were very ingrained in the way things had been done previously.

9.         I certainly cannot remember a case where I have spent 20 minutes on the phone with any miscellaneous member of staff while I have been on Control. I do not or have not, spent more time on an issue than is necessary.

10.     The "going around the houses" phrase does strike a bell.  From what 1 can recall, when setting up the computerisation for the miscellaneous system, 1 noticed certain anomalies.  One related to the way that a third party document asking for an account is set up by the Miscellaneous section.  In this procedure, the document would arrive in Miscellaneous and the on-line system would set up the account but no record would ever be kept of the documentation that was used to set it up.  This was returned to the user without keeping a copy.  This would mean that incorrect details had been set up, there was no copy to refer to.

11.     I pointed this out to Taras Fortuna, a Senior Officer and he did not understand why this was the case. I thought I would try to investigate this as it seemed to be a very poor control in their procedures.

12.     I then asked one of the Miscellaneous clerks about this procedure and they were also puzzled to why it worked in this way.

13.          I was very surprised that when I asked Patrick Rushgrove about this apparent malpractice, he became very agitated and told me not to investigate this any further.

14.          Of course, I was surprised but did what he asked.  He did use the phrase "going around the houses". I suspect that he must have contacted MS who, no surprise, again took the view that Control were totally in the wrong and did not follow it up with myself or any of the Control staff who also had the same question as myself regarding this issue.

15.          The Conflict regarding the priority between the Ctax Reminders and Misc. output. 1 cannot remember any problems with this apart from the Ctax Reminders being given priority in posting out when there was a Ctax Reminder run.  This was an instruction given by John Hawkes at the time and the priorities needed to be resolved at management level.  The instruction was from the Assistant Director for the reminders to have priority.

16.          I don't understand where this comes into the original subject of approachability.

17.          The Internal Mail.  When we took the Miscellaneous system over on Control, it was found that invoices were distributed by hand throughout Britannia House.  This was a very inefficient method of accomplishing a task which the Internal Mail had been designed for.

18.         The invoices were sent by internal mail from that point on.  After a few months, a slight problem occurred with the internal mail delivery of the invoices for Nick Woodhouse.  This was reported to Mike Porter in Miscellaneous who told me that he wanted the invoices delivering by hand.

19.        This system was very time consuming as the invoices would be taken to the different sections within HB and then mail would be picked up from HB and taken back to Miscellaneous.

20.          My response to Mike was that it was no longer possible to continue the method which Miscellaneous had used as a far simpler method had been devised.  Control simply did not have the time to deliver these items by hand.  Mike replied that Miscellaneous had the time to do it so why didn't Control.  This was a fact, as the increased workload within Control did not allow us to do this.  The methods which we employed at that time are still working efficiently and 1 feel that sometimes you can't please everyone in getting a section to work at its optimum.

21.             Girish also refers to the "sager is still continuing 3 weeks later'. I have to admit that I have never had the opportunity to be involved in a sager.

22.              Problems in dealing with the output. I have always been reluctant to accept blame for these problems until I am convinced that Control are at fault.  There is a reason for this.

23.              Patrick Rushgrove has been known to call around to Control and complain that output was posted out to the users rather than being returned.  On investigation, it was found that the output is first passed around to Miscellaneous and it is their staff who post out the invoices.

24.              Other instances showed that pullouts have been requested for invoices and the invoices are then sent out incorrectly by miscellaneous staff.

25.              Other investigations have shown similar results

26.              These type of incidents has led me to be slightly reluctant when blame is passed onto Control staff. 1 do admit though that when you deal with thousands of invoices, it is possible that mistakes can be made.  Procedures are always kept as tight and as updated as possible.

27.              I do not understand what the alleged problems in dealing with the dispatch invoices and those marked for return have to do with the original issue raised by this letter of approachability.

28.              I am certain that the direction in this letter came from MS, although probably written by GM.

29.              Here is another example of where MS is unwilling to support his Control team.  This has always been the case since I can remember.  It makes it very difficult to work efficiently when your own manager is unwilling to back your decisions.

30.              Overall, these were teething troubles in the implementation of the Miscellaneous system under Control and the resentment by Miscellaneous managers to accept this.

31.              Despite this, the transfer has worked very well as have the procedures and relations are good between the sections.

32.              Girish also mentions " and the manor you handle situations". I have never lived in a manor.

33.              MS has resurrected this letter from the archives to try to show that 1 have a history of non co-operation but the truth is that these issues would not be raised if he showed more support as a manager for his staff.  His lack of any resolve causes these to be made into bigger issues in the first place.

 

 

 


30.       These issues are not isolated incidents, can you explain your conduct (refer to other incidents as appropriate).

 

People say things to you and the incidents are blown up out of all proportion, they are all resolved now

 

I do not consider my conduct to be any worse or better than anyone else. I am reasonably friendly to all and make efforts to keep things running smoothly. From these four “incidents” quoted, I am certain that far worse things happen within Income Unit and they are resolved very quickly. MS and DL are blowing as much as possible out of proportion.

 

31.       Why did they need resolving?

 

As team leader I have to make sure things are working correctly. These are about control procedures and the need to make things run more efficiently. 

 

As answered.

 

32.       Do you understand that as a Team Leader responsible for staff that you have an additional responsibility to set examples and to carry out reasonable Management instructions appropriately and within a reasonable time?

 

Yes and yes

I have a very efficient team and everybody works well.

 

As answered.

 

33.       What about the efficiency of relationships.

 

OK now in his opinion

Apart from those with MS and DL which have led to the current problems. These problems are not due to myself but to the heavy handed approach taken.

 

The Management Interview was now adjourned.

The Management Interview reconvened at 2.00pm.

 

The following questions were repeated:-

 

Sanderson Software

 

15.       I asked for you view on the Sanderson inspection procedure on 2/2/99.  You did not respond so I followed this up with some alterations on 8/2/99.  These procedures involved control running various jobs, why did you not respond to this?

 

16.       Once this became an issue you met with DL in MS' office for approx. 3 hours and said you thought he was joking.  What did you find was amusing about this?

 

Joseph produced a typed statement that he read out (attached).  Joseph reiterated that he had had more time to consider the answer to these questions and would wish to do so for the others.

 

It was agreed that the notes of the meeting would be typed up and a copy sent to Joseph who would amend any areas of accuracy from the notes of the meeting and produce separate additional information as necessary on a separate sheet of paper for management to consider.

 

The notes would be sent to Joseph on Monday.

 

Joseph to E-mail Tim on Wednesday with an indication of when he would be able to return the notes.

 

Following Management's consideration of the notes and any additional information a further interview would probably be necessary.

 

The interview concluded at 2.30pm.

 

 

 


The following questions & comments were add in JB's document received on 16 July 1999

 

The Ongoing 1st Transcript: My concerns

The original management letter refers to the management concerns about my supposed non-co-operation with management.  Some of the questions raised in the transcript, although 1 have tried to answer them as best as 1 can, do not appear to relate to this issue.

1 .   Would it be possible for Ms to give me the reason why each question was asked, as many of them do not appear to have gone against management requirements.  For example, why was the question asked regarding the CUK3?  The explanation had already been given that this had become too complex.  Why does MS think that this is non co-operation with management?  If he thinks this, then the reasons should be stated.  Otherwise, this should be highlighted in the transcript as not being relevant.

2.         I answered these questions because 1 was asked to but 1 cannot understand why many of these questions were even asked.

3.         It has been brought to my attention that in further disciplinary events, this transcript would be used by management as evidence.

4.         In the light of this, I do not consider that the transcript to be complete or in line with the original concerns.  There are questions here that do not relate to the breaking of any management rules or requests.  Why did I need to be asked these questions and why did you feel that you needed answers to events do not relate to your concerns?

5.         The questions that were asked fell within certain events that may or may not have taken place.  The questions themselves add bulk to the document but if they were taken out, the areas which were misunderstood or taken out of all proportion by MS can be more accurately dealt with.

6.         The answers that were originally documented by management are no indication of what was said at the interview.  Management have stated that this was actually said.  The parts which they chose to document are very brief and when 1 have read through them leave me with the question of who said this. I certainly do not express myself in that way.

7.         Although the management-documented answers have been left in the transcript, it is not accurate to say that they resemble the actual answers given.  Any words or phrases can be taken out of context, and were taken out of context to make it seem as though there was no reasonable explanation for the questions asked. I have had to spend many hours of my time to bring the answers more in line with what was said.

8.    I have taken another look at the transcript and feel that a closer inspection of this document is needed along with the original intent of the questions and why they were even there.

9.    There is also the question of where these questions came from.  Most of the issues here did not involve MS in any way.  They were passed onto MS by DL without seeking any clarification of them in the first instance.  Even though MS had not been involved with these supposed events, there was no attempt to document the background which was needed to answer the question.

10.     I have been told that I should comply with management instructions and that there is a need to conclude the investigation as soon as practicable. 1 do not wish to appear to be obstructive but my concerns in this are genuine and 1 only wish to be as thorough as needed in giving answers to any management questions asked of me.  In the light of this and taking the above concerns into account, 1 will be ready to sign the transcript of the lst interview when you require.

I would be grateful if you could attach this as an appendix to the transcript so that these concerns will be read by anyone reading the transcript itself.